Reality Check: Is saving the Streetcar Project really feasible?

Posted: Updated: May 1, 2013 10:00 PM
  • Related LinksMore>>

  • City releases plan to fund over-budget streetcar

    City releases plan to fund over-budget streetcar

    April 30, 2013 10:43 PM 2013-12-02 20:47:12 GMT
    City Manager Milton Dohoney released a plan to pay for the over-budget streetcar project on Tuesday. The project is facing a $17.4 million gap.
    City Manager Milton Dohoney released a plan to pay for the over-budget streetcar project on Tuesday. The project is facing a $17.4 million gap.
  • Streetcar public meeting calls for answers

    Streetcar public meeting calls for answers

    Monday, April 29 2013 11:20 PM EDT2013-04-30 03:20:47 GMT
    It was a packed house Monday night at a public hearing designed to get some answers about the troubled downtown streetcar project. Vice Mayor Roxanne Qualls called the hearing hoping to get an update
    It was a packed house Monday night at a public hearing designed to get some answers about the troubled downtown streetcar project. Vice Mayor Roxanne Qualls called the hearing hoping to get an update on the status on the much-delayed project.
  • Streetcar misses critical date on completion timeline

    Streetcar Project passes date planned to begin work

    Friday, April 12 2013 8:25 PM EDT2013-04-13 00:25:47 GMT
    The Cincinnati streetcar project has passed a critical date on its timeline towards completion. In the manuals used by all of the contractors bidding on the project, the City clearly states the "notice
    In the manuals used by all of the contractors bidding on the project, the City clearly states the "notice to proceed" was planned for April 8th and the work then had to begin within five days.
CINCINNATI, OH (FOX19) -

The controversy surrounding Cincinnati's streetcar just won't go away. 

In fact, it has only intensified since FOX19 began asking for status updates on the project and budget.

Since we requested those documents, the city administration has turned over documents showing just how far off budget the project is.

So the big question tonight, is the project even financially possible at this point?

Ben has the Reality Check you won't see anywhere else.